Can a Contractor Demand Extra Payment Beyond the Original Agreement in the Philippines?

Quick answer

Usually, no—not if the contractor accepted a fixed or lump-sum price for the agreed plans, specifications, and scope of work.

Under Article 1724 of the Civil Code, a contractor generally cannot increase a stipulated price merely because labor, materials, transport, or other inputs became more expensive. For additional payment arising from changed plans or specifications, two things ordinarily must exist:

  1. The owner authorized the change in writing; and
  2. The parties determined the additional price in writing.

A contractor may nevertheless have a valid claim when the original contract already permits price adjustments, the work is genuinely outside the original scope and was covered by a proper written change order, the contract uses unit rates or actual-cost pricing, or another contractual or legal remedy applies. The exact result depends on the complete contract documents, the authority of the person who approved the work, and the records created before the extra work began.

The starting point: the agreed contract controls

Contracts have the force of law between the parties and must be performed in good faith. The first task is therefore to identify exactly what the parties agreed upon—not merely what appears in the quotation’s total-price line.

Review all documents incorporated into the agreement, including:

  • The signed construction contract or accepted proposal;
  • Plans, drawings, specifications, and revisions;
  • The bill of quantities or schedule of values;
  • General and special conditions;
  • Scope inclusions and exclusions;
  • Site-inspection and soil-condition provisions;
  • Price-escalation or adjustment clauses;
  • Variation and change-order procedures;
  • Notice and claim deadlines;
  • Provisions identifying who may approve additional work;
  • Emails, letters, minutes, instructions, and approved shop drawings; and
  • Later amendments or supplemental agreements.

Article 1159 of the Civil Code of the Philippines states that contractual obligations must be complied with in good faith. Parties may establish their own lawful terms, but neither side may unilaterally rewrite the price or scope after the agreement has been made.

Fixed-price and lump-sum contracts

A fixed-price or lump-sum contract ordinarily places on the contractor the risk that its estimate will prove too low. If the agreed work has not changed, the contractor generally cannot charge more simply because:

  • Cement, steel, fuel, or other materials increased in price;
  • Wages or subcontractor quotations rose;
  • The contractor underestimated quantities;
  • The work was more difficult or costly than expected;
  • The contractor omitted an item that was already part of the plans or specifications; or
  • The contractor’s anticipated profit disappeared.

Article 1724 expressly provides that a contractor who undertakes work for a stipulated price, in conformity with agreed plans and specifications, cannot demand an increase because of higher labor or material costs. The statutory exception applies when the plans or specifications change and both the written-authorization and written-price requirements are satisfied.

In Leighton Contractors Philippines, Inc. v. CNP Industries, Inc., the Supreme Court explained that a fixed lump-sum contractor assumes risks such as errors in measurement and price changes within the agreed scope. The Court also emphasized that receiving a cost estimate or signing a progress report does not necessarily prove that an authorized person approved an extra charge.

When extra payment may be justified

A properly approved change in plans or specifications

A contractor has the strongest claim when, before the changed work was undertaken:

  • The owner or an authorized representative issued or approved a written change;
  • The document clearly described the added or revised work;
  • Both parties agreed in writing on the added price or a definite method for calculating it; and
  • Any corresponding extension of time was also addressed.

A sound change order should identify the affected drawings, quantities, unit rates, taxes, completion date, and effect on previous work. A vague instruction such as “please proceed” may establish that someone wanted the work done, but it may not satisfy Article 1724’s separate requirement that the additional price be determined in writing.

The Supreme Court has repeatedly treated both requirements as conditions that must be met before additional costs may be recovered. See Salvador v. Court of Appeals and Titan-Ikeda Construction and Development Corporation v. Primetown Property Group, Inc..

The original contract contains an adjustment mechanism

Article 1724 does not turn every construction agreement into an unchangeable lump-sum contract. The parties may agree in advance to mechanisms such as:

  • Unit-price measurement;
  • Cost-plus compensation;
  • Reimbursable expenses;
  • Price escalation tied to a defined index or event;
  • Provisional sums;
  • Allowances for specified materials;
  • Daywork rates; or
  • Adjustments for expressly identified contingencies.

If such a clause applies, the contractor must follow its formula, documentation requirements, approval process, and notice deadlines. A general statement that prices are “subject to change” may be disputed if it does not specify when and how the adjustment is computed.

The requested work is genuinely outside the original scope

Work may be additional if it was not reasonably included in the original drawings, specifications, bill of quantities, or contractual completion obligations. Examples may include an owner-requested room extension, a materially different finish, or a new system added after contract signing.

The label is not decisive. Calling something “extra work” on an invoice does not make it extra. Conversely, the absence of a separate line item does not automatically make work additional if the contract required a complete functioning result or incorporated drawings showing that work.

For a stipulated-price project, even genuinely changed work ordinarily still requires the writings specified in Article 1724. In BTL Construction Corporation v. Court of Appeals, the Supreme Court again held that written authorization and a written agreement on price are required for added costs resulting from changed plans or specifications.

The owner prevents or delays performance

A claim caused by the owner’s acts may be legally different from a demand to raise the price because materials became more expensive. Article 1721 of the Civil Code provides for reasonable compensation when an act required from the employer is delayed or not performed. It also addresses situations where the work cannot be completed, without the contractor’s fault, because of defective owner-supplied materials or the owner’s orders.

Possible claims may involve documented standby costs, prolongation expenses, additional mobilization, or compensation for work already performed. They are not automatic. The contractor must prove the contractual basis, causation, actual loss, compliance with notices, and reasonable efforts to reduce the loss.

The owner cancels the work

Under Article 1725, an owner may withdraw from the construction even after it has begun, but must indemnify the contractor for expenses, work performed, usefulness obtained, and damages as legally established. This is different from allowing the contractor to unilaterally increase the price of work that remains within the original contract.

There was no stipulated price

If no fixed price was agreed, compensation may have to be determined under the contract’s actual-cost or unit-rate mechanism, or under the Civil Code rules applicable to a contract for a piece of work. This requires a fact-specific assessment. Courts and arbitrators will examine what the parties agreed, their conduct, customary rates where relevant, and reliable proof of labor and material costs.

Verbal instructions are dangerous

A site owner may casually ask for changes during an inspection. An architect, foreman, engineer, family member, tenant, or project manager may also give instructions. Those instructions create serious payment risk unless the contract identifies that person as authorized to bind the owner.

For a fixed-price project, the safest course is to stop the affected portion long enough to obtain a written change order signed by properly authorized persons. It should settle both the scope and price before work begins.

Contractors should not assume that photographs, oral testimony, delivery receipts, or proof that the owner benefited from the work will replace Article 1724’s required writings. In Titan-Ikeda, the Supreme Court held that a contractor lacking written authority for the change and written assent to its cost could not avoid the rule merely by invoking unjust enrichment.

Owners, meanwhile, should not knowingly direct extra work and postpone the price discussion. That practice invites factual disputes over authorization, contract modification, delay, and damages.

Does an email or message count as a writing?

Electronic records may have legal effect under the Electronic Commerce Act, but their sufficiency in a particular dispute depends on authenticity, content, attribution, and the contract’s own requirements.

An email or message is more useful when it clearly shows:

  • The sender’s identity and authority;
  • The precise change being approved;
  • The exact added price or an agreed calculation;
  • Acceptance by both parties; and
  • The date of approval before performance.

A message from an unauthorized site employee, a “seen” indicator, or an acknowledgment of receipt is not necessarily approval. If the contract requires a signed formal change order, comply with that procedure rather than relying only on an informal chat.

What an owner should do after receiving an extra-charge demand

Do not immediately accept or reject the entire demand without examining the documents.

  1. Request an itemized written claim. Ask the contractor to identify every alleged change, its instruction date, approving person, supporting drawing, quantity, unit rate, and effect on the schedule.

  2. Compare it with the original scope. Check the contract, exclusions, plans issued for construction, specifications, and bill of quantities.

  3. Verify authority. Determine whether the person who supposedly ordered the work was authorized under the contract or by a separate written authority.

  4. Separate categories. Distinguish original-scope work, approved variations, disputed variations, owner-caused delay claims, and correction of defective work.

  5. Respond in writing. State which items are admitted, disputed, or require further support. Avoid language that could unintentionally confirm liability.

  6. Pay undisputed amounts when due. Withholding an admitted progress payment merely because another item is disputed may itself constitute a breach, depending on the contract.

  7. Check warranties and defects. An extra-payment claim does not excuse defective or incomplete work, but alleged defects should be documented and handled under the contract rather than used as an unsupported reason to withhold everything.

  8. Follow the dispute clause. Observe any negotiation, engineer’s determination, mediation, adjudication, or arbitration procedure.

What a contractor should do before performing additional work

  1. Issue a written notice identifying why the instruction changes the original scope.
  2. Cite the relevant plan, specification, exclusion, or bill-of-quantities item.
  3. Submit a priced variation with quantities and supporting quotations.
  4. State the effect on the completion date.
  5. Obtain written approval from the owner or the person expressly authorized by the contract.
  6. Ensure that the added price—or an objective pricing method—is accepted in writing by both parties.
  7. Keep separate daily records for additional labor, equipment, and materials.
  8. Do not treat silence as approval unless the contract and applicable law clearly support that conclusion.
  9. If urgent safety work cannot reasonably wait, send immediate written notice, preserve proof of the emergency, minimize costs, and obtain legal advice promptly.

Evidence both sides should preserve

Keep original or reliably backed-up copies of:

  • The signed contract and all incorporated documents;
  • Every version of the plans and specifications;
  • Tender clarifications and accepted exclusions;
  • Change orders and variation proposals;
  • Emails, letters, text messages, and meeting minutes;
  • Site instructions and requests for information;
  • Daily logs, manpower records, and equipment reports;
  • Dated photographs and videos;
  • Purchase orders, invoices, receipts, and delivery records;
  • Progress billings and payment certificates;
  • Inspection, punch-list, and acceptance records;
  • Construction schedules and approved extensions; and
  • Documents showing the authority—or lack of authority—of the person who issued an instruction.

Preserve native electronic files and message exports where possible, not only screenshots. Do not alter dates, annotations, or metadata.

Common mistakes

Starting extra work before agreeing on the price

This is the most serious contractor-side error under Article 1724. Written approval of the design change alone may be insufficient if the additional price was never determined in writing.

Assuming every site instruction binds the owner

Authority matters. A person may have authority to inspect work but not to alter scope, approve cost, or extend time.

Treating a cost increase as a scope change

Inflation or a supplier price increase does not by itself change the plans or specifications. A fixed-price contractor generally bears that risk unless an adjustment clause applies.

Ignoring documents incorporated by reference

A quotation may appear to omit an item, while the signed contract incorporates drawings or specifications that include it. The documents must be read together.

Using acceptance or occupancy as automatic proof of an approved variation

Use of the completed structure may be relevant to some issues, but it does not automatically satisfy Article 1724’s written requirements.

Missing notice deadlines

Construction contracts commonly require notice within a short period after an instruction, delay, or unforeseen condition. Failure to comply can jeopardize an otherwise arguable claim. The applicable period comes from the particular contract, so act immediately rather than waiting for final billing.

Withholding all payments because one variation is disputed

A dispute over extra work does not necessarily eliminate the duty to pay certified, accepted, or otherwise undisputed original-contract work.

Special rules for government infrastructure projects

Public projects are subject to procurement and auditing rules in addition to the Civil Code and the contract. A contractor should never rely on an informal instruction from a government employee as authority to perform chargeable additional work.

Under Section 71.2.1 of the current Implementing Rules and Regulations of Republic Act No. 12009, variation orders may cover quantity changes, new work items, or reclassification caused by changes in plans, design, alignment, or qualifying site conditions. Among the principal rules:

  • Positive variation orders generally may not cumulatively exceed 10% of the original contract price.
  • Work beyond 10% should generally be treated as another procurement if separable.
  • In exceptional and urgent cases necessary to complete the original scope, the Head of the Procuring Entity may authorize cumulative positive variations above 10% but not more than 20%.
  • Added work must remain within the project’s general scope as bid and awarded.
  • A contractor ordinarily must not commence work under a change or extra-work order without the prescribed approval, subject to the limited immediate-start conditions in the IRR.
  • Approved additional work is priced under the applicable original unit prices or the prescribed method for new work items.

Projects procured during a transition period may remain governed by earlier procurement rules and their own bid documents. The procurement law, applicable IRR edition, funding authority, approved variation order, and audit requirements must therefore be checked for the specific project.

Resolving a dispute

Start with the dispute-resolution procedure in the contract. A well-prepared written position should identify:

  • The contractual provision relied upon;
  • The original and allegedly changed scope;
  • The written authorization;
  • The written price agreement;
  • The authority of each signatory;
  • The amount claimed or disputed;
  • The effect on time; and
  • The proposed resolution.

Construction disputes involving payment, changes in contract cost, specifications, delay, defects, or contract interpretation may fall within the Construction Industry Arbitration Commission’s jurisdiction when the required agreement to arbitrate exists. Section 4 of Executive Order No. 1008 covers disputes connected with public or private construction contracts, including disputes arising after completion, abandonment, or breach.

An arbitration clause in a Philippine construction contract can be sufficient consent to CIAC jurisdiction even if the clause refers generally to arbitration or names another arbitral body. Forum selection should therefore be reviewed before filing a court case.

Deadlines and when legal help is urgent

Do not assume there is time to wait until project completion. Seek construction-law advice promptly when:

  • Work is about to be concealed, demolished, or taken over;
  • The owner or contractor threatens termination or abandonment;
  • A large variation is being performed without a signed price;
  • Payment certificates, retention money, or performance security are at risk;
  • The contract contains a short notice or claim deadline;
  • A government employee directed unapproved additional work;
  • The parties disagree over who had authority to approve a change;
  • A demand, notice of arbitration, or court pleading has been received; or
  • Evidence, personnel, or site access may soon disappear.

As a general Civil Code rule, an action upon a written contract must be brought within 10 years from accrual, while an action upon an oral contract generally must be brought within six years. These periods do not override valid contractual notice requirements, arbitration procedures, special statutory rules, or a different legal characterization of the claim. Accrual and interruption of prescription can also be disputed, so these outer periods should never be treated as safe waiting periods.

Frequently asked questions

Can a contractor charge more because material prices increased?

Generally not under a fixed-price contract. An enforceable escalation or adjustment clause may produce a different result.

What if the owner verbally requested the additional work?

The contractor may face serious difficulty recovering under Article 1724. For a stipulated-price project, the owner’s authority for the changed plans or specifications and the additional price ordinarily must both be in writing.

Is a signed change order enough?

Only if it adequately covers both requirements: authorization of the change and written agreement on the additional price or a sufficiently definite pricing method. The signer must also have authority.

Can the contractor stop work if the owner refuses the extra payment?

Not automatically. Wrongful suspension or abandonment can itself be a breach. The contractor should examine the payment, suspension, notice, and termination clauses and obtain advice before stopping work.

Can an owner refuse every extra charge because the contract says “lump sum”?

Not necessarily. A lump-sum label does not authorize an owner to demand materially changed or new work for free. A properly documented variation, an express adjustment clause, owner-caused delay, or another applicable contractual remedy may support additional compensation.

Can a contractor claim unjust enrichment when the owner benefited from unauthorized extra work?

That argument is unsafe in a fixed-price change-order dispute. The Supreme Court has held that a contractor who failed to obtain the writings required by Article 1724 could not use unjust enrichment to bypass those requirements.

Does payment of an earlier extra-work invoice approve later extras?

Not by itself. Each disputed item must be evaluated against the contract, the parties’ written communications, the approving person’s authority, and any course-of-dealing provision.

Who decides if the parties cannot agree?

The proper forum depends on the contract and facts. A construction arbitration agreement may place the dispute within CIAC’s original and exclusive jurisdiction; otherwise, another agreed arbitration process or the proper court may apply.

Official legal sources

This article provides general legal information, not legal advice for a particular contract or dispute. Construction claims are highly document- and fact-dependent. Official sources and current procedures were checked as of July 27, 2026.