This guide collects the key rules, typical contract mechanisms, and practical playbooks an owner can use when a project slips or the works are defective. It focuses on private building projects (with notes for government contracts), Philippine civil law, and common industry standards (e.g., CIAP forms).
1) Sources of Rights and Remedies
The Contract. Your first resort. It sets deadlines, quality requirements, testing/commissioning, variation procedures, extension-of-time (EOT) rules, liquidated damages (LDs), retention, bonds, and the defects liability period (DLP).
The Civil Code.
- General breach remedies (rescission/termination under Article 1191, specific performance, and damages).
- Penalty clauses (Articles 1226–1230) let parties pre-agree LDs; courts may reduce unconscionable penalties.
- Force majeure (Article 1174) excuses delay if truly unforeseeable/inevitable and not assumed by the obligor.
- Contracts for a piece of work (Articles 1713–1720) and architect/engineer/contractor liability (Article 1723) for ruin or serious defects of buildings.
Special regimes and industry practice.
- CIAC arbitration (Executive Order No. 1008) for construction disputes when there’s an arbitration agreement (and in some cases by referral).
- CIAP standard forms (e.g., CIAP Doc. 102 for buildings) widely used in private projects: they provide a one-year DLP, LDs for delay, retention, and claims procedures.
- Public projects (RA 9184 and IRR): special rates for LDs, blacklisting, and DPWH/agency specifications.
Regulatory & licensing hooks.
- PCAB licensing (contractor must be properly licensed).
- Building Code/permits and professional accountability of architects/engineers.
2) Delay: Owner’s Tools
A. Diagnose the Delay
- Critical path delay vs non-critical (only the former affects completion date).
- Excusable (e.g., force majeure, owner variations, authority-caused) vs non-excusable (contractor’s fault).
- Compensable (owner-risk events) vs non-compensable (neutral events that only justify time, not money).
Evidence to gather: approved programme, updated look-aheads, daily reports, permits/utility clearances, weather logs, RFI/VO logs, correspondence, site instructions, meeting minutes, inspection photos, and expert delay analysis (e.g., time-impact analysis).
B. Contractual Remedies
Withhold/offset
- Retention money (commonly 10% of progress payments until a cap, then released half upon taking-over, balance after DLP).
- Set-off LDs or rework costs against progress bills.
Liquidated damages (LDs)
- Payable per day of delay beyond the time for completion (substantial completion/taking-over date).
- Function as a penalty/estimate of loss; courts may reduce if iniquitous, but LDs are usually enforced when commercially reasonable and negotiated.
Performance security
- Performance bond (surety) callable for default;
- Warranty/defects bond for DLP;
- Advance payment bond (to protect the mobilization). Callability depends on bond wording (on-demand vs conditional) and proof of default.
Step-in rights and termination
- Step-in to perform or engage a replacement after notice and cure periods.
- Termination for default if delay is substantial and uncured; recover completion and acceleration costs from the contractor and its surety.
- Termination for convenience (if allowed by contract) with agreed compensation formulas.
Acceleration
- Owner may instruct acceleration; contractor may claim costs only if the contract or instruction entitles it (e.g., compensable acceleration).
- If the contractor accelerates voluntarily to mitigate LDs, costs generally aren’t reimbursable.
Re-baseline/EOT discipline
- Enforce claims windows (e.g., notice within 7–28 days) and substantiation. Late or unproven EOT claims can be barred.
C. Civil Code Remedies (outside or alongside the contract)
Specific performance (finish by a court-set date) with damages.
Rescission/termination (Article 1191) for substantial breach; recover damages.
Damages:
- Actual/compensatory (e.g., extended prelims, lost rent, financing, consultants).
- Penalty/LDs (if agreed).
- Interest (legal interest runs on monetary awards from judicial demand; rates follow prevailing jurisprudence).
- Moral/exemplary damages only for fraud/bad faith or wanton delay.
D. Force Majeure & Owner-Risk Events
- Contractor is excused (time, not money) for events that are unforeseeable and unavoidable and that actually prevented performance; documentation is crucial.
- If the owner’s acts caused delay (late drawings, site access, variation), the contractor may be entitled to EOT and cost; failure to honor may expose the owner to counterclaims—so assess fairly.
3) Defects: Owner’s Tools
A. Types of Defects
- Patent (discoverable upon reasonable inspection at or before taking-over).
- Latent (hidden; discovered later—often during/after the DLP).
- Non-conformance to specifications vs workmanship issues vs design defects (if design is owner-supplied or contractor-designed).
B. Contractual Architecture
Testing and commissioning
- Pre-handover tests, punchlists, and Taking-Over Certificate (or Substantial Completion).
- A taking-over does not waive latent defects unless expressly stated.
Defects Liability Period (DLP)
- Commonly 12 months from taking-over. Contractor must make good any defects notified within the DLP at its own cost.
- If not cured, the owner may rectify at the contractor’s cost (draw on retention/warranty bond).
Warranties
- Materials/equipment warranties from suppliers (often 1–2 years; longer for roofs, waterproofing, chillers, elevators).
- Fitness for purpose obligations if expressly assumed (more common in design-build).
- Statutory liability (Article 1723): architects/engineers/contractors are liable for ruin or serious defects of buildings due to defects in design, materials, or construction occurring within a long warranty period (commonly understood as 15 years from completion), with a prescriptive period to sue thereafter. Acceptance by the owner does not bar this liability.
Security
- Warranty/Defects bond (released after DLP if no outstanding claims).
- Manufacturer guarantees and as-built documentation (maintenance manuals, O&M training).
C. Civil Code Backstops
- Specific performance (order to repair/replace).
- Rescission and price reduction for substantial defects.
- Damages for consequential losses (e.g., water ingress damaging interiors; rental loss during shutdown).
- Professional negligence against designers/supervisors when their acts caused the defects (duty of care and contract duties).
D. Evidence & Process
- Maintain a defects register, dated photos, test reports (e.g., core tests for concrete, pull-out tests, waterproofing flood tests), inspection requests (IRs), non-conformance reports (NCRs), and corrective action reports (CARs).
- For building envelope/MEP issues, secure independent experts (e.g., façade consultants, commissioning agents) early.
- Preserve samples and failed components where feasible.
4) Money: How Recovery Is Calculated
Liquidated damages (delay)
- Daily rate × days of culpable delay (after netting any granted EOT).
- Courts may moderate excessive LDs; keep rates proportionate to likely owner loss (financing, rent, prelims).
Direct cost of completion
- If you terminate and replace the contractor, you can claim the excess completion cost plus professional fees, temporary works, and acceleration necessary to meet the revised date.
Cost to cure defects
- Reasonable repair/replacement costs, temporary relocation, access/scaffolding, testing/commissioning repeats, and resulting damage.
Consequential losses
- Lost rentals/operations, increased financing. Recovery depends on contract wording (some exclude consequential damages).
Interest
- Monetary awards accrue legal interest from judicial or demand dates per prevailing jurisprudence.
5) Procedure and Forums
A. Dispute Resolution Lanes
Engineer’s/Architect’s decision or Dispute Board (if provided).
Mediation (often fast and inexpensive).
Arbitration
- CIAC is the sector-specialized forum for construction disputes when the arbitration clause or later referral places the dispute there; streamlined rules and technical expertise.
- Commercial arbitration (ad hoc or institutional) under the ADR Act.
Courts (for injunctions, bond calls, or when no arbitration path is available).
Urgent relief: apply for interim measures (e.g., to stop wrongful bond calls or preserve evidence) via courts or arbitral tribunals, as allowed by the ADR framework.
B. Prescription (limitation) checkpoints
- Written contract claims: typically 10 years from accrual of cause of action (e.g., non-payment, defective work claim when contractor refuses to cure).
- Quasi-delict: 4 years from injury.
- Article 1723 (ruin/serious defects): long warranty period (commonly treated as 15 years from completion), with a prescriptive period to sue thereafter; consult counsel to compute precisely (trigger dates and characterization matter).
- LDs: run with the underlying breach but are governed by the penalty clause and general prescription for written contracts.
Practice tip: Put your claims in writing early (reservation of rights), keep contemporaneous notices, and diary all claim windows (some CIAP/contract forms bar late claims).
6) Public-Sector Projects (Quick Notes)
- Liquidated Damages: calculated under the IRR (often around 0.10% of the contract price per calendar day of delay, capped).
- DLP: usually one year; retention and warranty security are standard.
- Blacklisting: repeat or serious default can lead to suspension/blacklisting under GPPB rules.
- Variation/Change Orders: capped percentages and approvals.
- CIAC also commonly used when contracts contain arbitration clauses.
7) Practical Playbooks
A. When Delay Hits the Critical Path
- Issue a notice of delay and request a recovery plan within a fixed period (e.g., 7 days).
- Enforce programme updates and time-impact analysis for any EOT claims.
- Start withholding LDs/retention offsets if allowed.
- Consider direct hire of critical trades/materials if contract allows step-in.
- If uncurable within a reasonable window, terminate for default, secure the site, inventory materials, and mobilize a completion contractor.
B. When Defects Surface
- Serve a Defects Notice identifying location, specification breached, and a cure deadline.
- Conduct targeted tests (e.g., water ponding for roofs, rebar scans, MEP commissioning).
- If uncured, rectify at contractor’s cost; call the warranty bond or draw on retention.
- For systemic defects or structural/performance risk, engage independent experts and consider Article 1723 claims against the contractor and professionals.
- Preserve evidence and maintain a cost-to-cure ledger for damages proof.
C. Bond Calling Checklist
- Confirm bond type (on-demand vs conditional).
- Check expiry and claims window.
- Compile default record (notices, cure, engineer’s certifications).
- File formal demand strictly per bond wording (service method, addressees).
- Prepare for injunctive challenges—ensure you have a clean paper trail.
8) Owner-Favorable Clauses (for future contracts)
- Clear time for completion with milestones and sectional completion.
- LDs at a commercially defensible daily rate with an overall cap (or without, if justified).
- Tight EOT notice windows and detailed substantiation requirements.
- Design responsibility allocation (fitness for purpose in design-build; reliance carve-outs where owner supplies design).
- Testing & commissioning regime; explicit taking-over criteria.
- DLP of at least 12 months, with extended special warranties (roofing/waterproofing/envelope/M&E).
- Retention plus performance and warranty bonds.
- Right to rectify and step-in for emergencies.
- Cap on contractor claims (e.g., exclude consequential loss) while preserving owner’s rights to LDs and cost-to-complete.
- Arbitration clause designating CIAC (or institutional rules) with seat/place, language, and interim measures.
- Records & audit rights; digital project controls (BIM, CDE, e-RFI).
9) Evidence & Damages Strategy
- Keep monthly cost reports, owner’s extended preliminaries, interest calculations, and rent/operations loss models.
- Align expert evidence: delay analyst, QS, forensics engineer, commissioning agent.
- Track mitigation steps (acceleration offers, temporary works) to protect recovery and defeat “failure to mitigate” defenses.
10) Quick FAQs
Q: Can we claim LDs and actual damages together? Generally no for the same head of loss—LDs replace proof of actual delay loss unless the contract allows additional recoveries (e.g., LDs for delay plus separate cost-to-cure defects).
Q: Does taking-over waive defects? Not for latent defects and not for obligations under Article 1723; but patent defects listed in a punchlist must be acted on within the DLP.
Q: Contractor blames force majeure. What now? Require timely notice, causation proof, and mitigation. Many “bad weather” or supply issues are foreseeable market risks, not force majeure.
Q: When should we go to CIAC vs court? If your contract has an arbitration clause, expect CIAC (or your chosen institution). You can seek interim court relief without waiving arbitration.
11) Owner’s Document Pack (ready-to-use outlines)
- Notice of Delay: date, event, impacted activities, required recovery plan, LD reservation.
- Defects Notice: location, spec reference, evidence, cure-by date, access coordination.
- Notice of Default & Termination: breaches, cure period, step-in/termination basis, bond calls, turnover demands.
- Bond Demand Letter: attach certificates, notices, quantification, and compliance with bond terms.
- Taking-Over Certificate & Punchlist form.
- DLP Defects Register with status and response deadlines.
12) Final Pointers
- Front-load clarity in contracts; dispute outcomes often mirror drafting quality.
- Police the programme (updates, approvals, early warnings).
- Write early, write often: notices preserve rights.
- Keep claims proportionate and evidence-backed to survive moderation of LDs and scrutiny of cost-to-cure.
- Loop in counsel and experts early for structural defects or when termination/bond calls are on the table.
This article is for general guidance within the Philippine legal framework. Particular facts, contract wording, and forum choices can change outcomes; consult counsel for specific matters.