Contractor’s Rights on Construction Contract Termination and Liquidated Damages (Philippines)

Contractor’s Rights on Construction Contract Termination and Liquidated Damages in the Philippines

Introduction

In the Philippine construction industry, contracts form the backbone of projects ranging from residential buildings to large-scale infrastructure developments. These contracts are primarily governed by the Civil Code of the Philippines (Republic Act No. 386), which provides general principles on obligations and contracts, supplemented by specific laws such as Presidential Decree No. 1594 (Prescribing Policies, Guidelines, Rules and Regulations for Government Infrastructure Contracts) for public works, and Republic Act No. 9184 (Government Procurement Reform Act) for procurement processes. Private construction contracts may also incorporate standards from the Construction Industry Authority of the Philippines (CIAP) and international frameworks like FIDIC (Fédération Internationale des Ingénieurs-Conseils) conditions, adapted to local law.

A critical aspect of these contracts is the provision for termination and the imposition of liquidated damages, which safeguard the interests of both owners (principals or employers) and contractors. Termination can occur for various reasons, including breach, convenience, or force majeure, while liquidated damages serve as a pre-estimated compensation for delays or non-performance. This article comprehensively explores the contractor's rights in the event of contract termination and the application of liquidated damages, drawing from statutory provisions, jurisprudence, and standard practices in the Philippine context. It examines the legal foundations, procedural requirements, remedies available to contractors, and limitations imposed by law.

Legal Framework Governing Construction Contracts

General Principles under the Civil Code

The Civil Code treats construction contracts as a species of obligations to do (Articles 1713-1729). Article 1724 specifically addresses building contracts, stipulating that the contractor is responsible for the work's execution in accordance with the plans and specifications agreed upon. The owner must pay the contract price, and any variations require mutual consent.

Key principles include:

  • Mutuality of Obligations: Both parties must fulfill their duties; failure by one may justify termination by the other (Article 1191).
  • Good Faith: Contracts must be performed in good faith (Article 1159), which influences interpretations of termination clauses.
  • Pacta Sunt Servanda: Agreements are binding, but courts may intervene in cases of inequity (Article 1306).

For government contracts, PD 1594 and RA 9184 impose additional layers, including competitive bidding, performance bonds, and strict accountability.

Standard Contract Forms

In practice, contracts often use templates from the Philippine Contractors Accreditation Board (PCAB) or CIAP Document 102 (Uniform General Conditions of Contract for Private Construction). These include clauses on termination, suspension, and damages, aligned with Civil Code provisions.

Termination of Construction Contracts

Termination disrupts the contractual relationship and triggers rights and obligations. Philippine law distinguishes between termination for cause, termination for convenience, and termination due to fortuitous events.

Termination for Cause

This occurs when one party breaches the contract materially. Common causes include:

  • Owner's Breach: Failure to pay progress billings, provide site access, or approve variations (Article 1724, Civil Code).
  • Contractor's Breach: Delays, substandard work, or abandonment (Article 1234 on slight breaches not warranting rescission).

Under Article 1191, the injured party may seek rescission (termination) with damages. For contractors, if the owner terminates for cause unjustly, it may be deemed wrongful, entitling the contractor to remedies.

In government contracts (PD 1594), termination for cause requires notice and opportunity to cure, with the government agency (e.g., DPWH) following due process.

Termination for Convenience

Many contracts, especially government ones, allow the owner to terminate without fault, often for public interest or project changes. RA 9184 and PD 1594 permit this, but the contractor is entitled to compensation for work performed plus reasonable profit.

Jurisprudence, such as in DPWH v. CMC/MONARK/PACIFIC Joint Venture (G.R. No. 179732, 2010), emphasizes that termination for convenience must not be arbitrary and should compensate the contractor fairly.

Termination Due to Force Majeure

Fortuitous events (Article 1174, Civil Code) like typhoons, earthquakes, or pandemics (as seen in COVID-19 cases) may lead to termination if performance becomes impossible. The contractor is not liable for delays caused thereby, but must notify the owner promptly.

In Robern Development Corporation v. Quitain (G.R. No. 135042, 1999), the Supreme Court held that force majeure excuses performance but does not automatically terminate unless stipulated.

Procedural Requirements for Termination

  • Notice: Contracts typically require written notice specifying grounds and a cure period (e.g., 15-30 days).
  • Documentation: The terminating party must substantiate claims with evidence, such as progress reports or inspection records.
  • Dispute Resolution: Clauses often mandate arbitration under the Construction Industry Arbitration Commission (CIAC) per Executive Order No. 1008, before court action.

Failure to follow procedures can render termination invalid, exposing the owner to liability.

Contractor's Rights Upon Termination

Upon termination, the contractor's primary rights revolve around compensation, recovery of costs, and protection against wrongful acts. These rights aim to restore the contractor to the position they would have been in had the contract been fulfilled or not breached.

Right to Payment for Work Performed

  • Quantum Meruit: If terminated without fault, the contractor is entitled to payment based on the value of work done (Article 1724). This includes materials supplied, labor, and equipment mobilization.
  • Progress Billings: Unpaid installments must be settled, with interest at the legal rate (6% per annum under BSP Circular No. 799, Series of 2013, unless stipulated higher).
  • Retention Money: Typically 10% of payments, this must be released upon termination if work is accepted, minus defects.

In National Power Corporation v. Ibrahim (G.R. No. 175006, 2011), the Court awarded quantum meruit recovery where the contract was terminated midway.

Right to Recover Costs and Profits

  • Mobilization and Demobilization Costs: Reimbursable if termination is not due to contractor's fault.
  • Expected Profits: For wrongful termination, contractors may claim lost profits (lucrum cessans) based on contract price minus costs saved.
  • Overhead and Indirect Costs: Allocable portions are recoverable.

Under PD 1594 for government contracts, termination for convenience entitles the contractor to 10-15% profit on unperformed work, plus costs incurred.

Right to Damages

  • Actual Damages: Proven losses, such as idle equipment or subcontractor claims.
  • Moral and Exemplary Damages: If termination is in bad faith (Article 2220), e.g., malicious intent.
  • Attorney's Fees: Awardable if stipulated or if the owner acted capriciously (Article 2208).

In Heirs of Pedro Atega v. Omega Construction (G.R. No. 202124, 2015), the Court upheld contractor's claims for damages due to owner's wrongful termination.

Right to Lien and Security

  • Mechanic's Lien: Under Article 2242, contractors have a lien on the property for unpaid work, enforceable via foreclosure.
  • Performance Bond: If called upon unjustly, the contractor can seek reimbursement from the owner.
  • Warranties: Post-termination, contractors remain liable for defects in completed portions but can counterclaim for owner's breaches.

Limitations on Contractor's Rights

  • Waiver Clauses: Contracts may limit rights, but these are strictly construed against the drafter (usually the owner).
  • Prescription: Claims prescribe in 10 years for written contracts (Article 1144).
  • Mitigation Duty: Contractors must minimize losses post-termination (Article 2203).

Liquidated Damages in Construction Contracts

Liquidated damages (LDs) are pre-agreed sums payable for breach, typically delays, to avoid proving actual damages.

Legal Basis

Article 2226 validates LD clauses if not iniquitous. They are enforceable unless proven excessive or if the breach is minor.

In construction, LDs are common for delays, calculated as a percentage of contract price per day (e.g., 1/10 of 1% under PD 1594).

Contractor's Rights Regarding Liquidated Damages

  • Challenge Enforceability: If LDs are penal (excessive), courts may reduce them (Article 2227). In SSS v. Moonwalk Development (G.R. No. 73345, 1993), LDs were tempered for partial performance.
  • Excusable Delays: Contractors can invoke extensions for owner-caused delays or force majeure, nullifying LDs (Article 1174).
  • Cap on Liability: Contracts often cap LDs at 10% of contract price.
  • Counterclaims: If owner delays payments, contractors can offset LDs against claims.
  • Proof of Actual Loss Not Required: LDs are payable regardless of actual damage, but contractors can argue no breach occurred.

Jurisprudence on Liquidated Damages

  • Filinvest Land, Inc. v. CA (G.R. No. 138980, 2000): Upheld LDs for delays but allowed reductions for good faith efforts.
  • DPWH v. Equital (G.R. No. 192975, 2014): Confirmed that LDs do not apply to excusable delays like weather events.

For government contracts, COA (Commission on Audit) Circulars ensure LDs are deducted fairly, with contractors able to appeal via CIAC.

Dispute Resolution and Remedies

Disputes over termination or LDs are resolved through:

  • Negotiation and Mediation: Initial steps per contract.
  • Arbitration: Mandatory for construction disputes under EO 1008, with CIAC having jurisdiction. Awards are final, appealable only on limited grounds.
  • Judicial Recourse: For non-arbitrable issues, courts apply Civil Code principles.

Contractors can seek provisional remedies like injunctions to halt wrongful termination (Rule 58, Rules of Court).

Conclusion

In the Philippine construction landscape, contractors hold substantial rights upon contract termination and in the face of liquidated damages, balanced against obligations to perform diligently. These rights—rooted in equity and statutory protections—ensure fair compensation and deter abusive practices by owners. However, enforcing them requires meticulous documentation and timely action. As the industry evolves with new laws and technologies, contractors must incorporate robust clauses to safeguard their interests, while owners should exercise termination powers judiciously to avoid costly litigation. Ultimately, mutual respect for contractual terms fosters successful project outcomes.