1. What “Defect Liability Period” Really Means

Key point Philippine practice
Definition A finite period (typically 365 calendar days counted from final acceptance or substantial completion) during which the contractor must, at its own cost, repair, replace or make good any defect in the works that becomes manifest.
Nature A contractual undertaking, reinforced by statute and public policy; meant to give the owner a reasonable “shake-down” interval to surface workmanship or material defects that ordinary inspection might miss.
Interaction with warranties DLP is not the same as:
Statutory hidden-defect warranty (Civil Code art. 1546, 1561)
15-year structural collapse liability (Civil Code art. 1723)
Product or manufacturer’s warranties on specific materials or equipment.

2. Core Legal Sources and How They Apply to Retrofitting

Source Salient provisions for buildings/retrofits
Civil Code (1949) Art. 1723 – architects, engineers and contractors solidarily liable for collapse within 15 years if due to design or construction defects or inferior materials.
Arts. 1715-1719, 1546-1561 – general contractor’s warranties and hidden-defect rules.
Presidential Decree 1096 (National Building Code, 1977) & IRR • Requires permits for alterations, additions or retrofitting; DPWH local building official may withhold Certificate of Occupancy until defects are cured.
RA 9184 & 2016 IRR (Government Procurement Reform Act) §62 imposes a one-year warranty on building projects; retention or warranty security (cash, bank guarantee or surety) = 5 % of the final contract price.
• For “infrastructure” (roads, bridges) period can run 3-5 years, but building retrofits generally fall under the one-year rule.
CIAP Document 102 / Philippine Domestic Construction Contract (PDCC) • Standard private-sector conditions: 12-month Defects Liability; empowers owner to retain 10 % until end of DLP or to draw on the contractor’s warranty bond.
RA 4566 (Contractors’ License Law) • PCAB may suspend/revoke a contractor’s license for refusal or failure to honor DLP obligations.
Local ordinances & DPWH Seismic Retrofit Guidelines • Some LGUs, especially in high-risk seismic zones (e.g., Metro Manila), embed mandatory DLP clauses in retrofit permits aligned with the latest National Structural Code of the Philippines (NSCP 2020).

Bottom line: even when the project is purely retrofitting, the standard 1-year DLP for buildings applies exactly as it does to new construction, unless the parties expressly extend it in their contract (which many owners now do, e.g., to 24 months for complex seismic upgrades).


3. Practical Operation of the DLP in a Retrofit Project

  1. Triggering point – runs from the date of final acceptance (often the same date the building official issues an amended Certificate of Occupancy reflecting the retrofit).

  2. Retention money / warranty security – released only after:

    • All punch-list items are cleared, and
    • The one-year period lapses without unresolved defects.
  3. Notification duty – owner must give written notice of each defect; silence does not waive hidden-defect claims or Article 1723 liability.

  4. Rectification window – contractor is usually given 30 days (or a period set in contract) to mobilize; failure lets owner draw on the warranty security or hire a third party at contractor’s cost.

  5. Overlap with design professionals – where the retrofit designer is a separate entity, the contractor often seeks a back-to-back indemnity; but Article 1723 makes all three (architect/engineer/contractor) solidarily liable to the owner in case of collapse.

  6. Insurance interplay – prudent contractors maintain Contractors’ All-Risk (CAR) and Professional Indemnity extending through the DLP; some owners require an Extended Maintenance Endorsement exactly matching the DLP.


4. Special Issues Unique to Retrofitting Existing Buildings

Issue Explanation Risk-mitigation tip
Latent-interface defects Failures at the “old-to-new” connection (e.g., dowel anchorage into existing columns) may show up only after cyclic loading months later. Specify longer DLP or separate “interface warranty clauses.”
Code-upgrade obligations If the NSCP is revised during DLP, owner may argue the retrofit should meet the new code. Courts / CIAC generally hold contractor liable only to codes in force at permit date unless contract says otherwise. Draft clear “code-freeze” clause.
Access for further testing Retrofitted shear walls or FRP wraps may be concealed; destructive testing to verify a defect can itself damage finished work. Include a testing protocol and cost-sharing terms in the contract.
Integration with fire-life-safety systems Penetrations through retrofitted elements can compromise rating. If a sprinkler contractor later creates the defect, who is liable? Stipulate joint inspection sign-offs and cross-indemnification among trades.

5. Jurisprudence Illustrating DLP-Related Liability

Case (G.R. No.) Core ruling Relevance to retrofits
Pineda v. Court of Appeals (105104, 28 Sep 1993) Builder held liable for latent concrete honeycombing discovered within DLP; owner properly withheld final payment. Confirms that owner’s right to retain is valid leverage during DLP.
F.F. Cruz & Co. v. Court of Appeals (77663, 29 Jun 1993) Collapse after 9 years triggered Article 1723; contractor and engineer solidarily liable despite previous DLP clearance. Shows DLP clearance does not cut off 15-year structural liability.
People v. Go Bio Bay (L-20691, 17 Aug 1967) Criminal negligence for fatal collapse due to sub-standard materials. Underscores that structural retrofits, if defective, may entail criminal as well as civil exposure.

6. Drafting & Contract-Management Checklist

  1. State the exact DLP length (default 365 days; consider longer for seismic retrofits).
  2. Require a warranty bond or retention equal to 10 % (private) or 5 % (public) of the contract price.
  3. Detail a defects-notification & cure timetable (e.g., written notice → site inspection → 30-day rectification).
  4. Back-to-back liability clauses tying designer and specialty subcontractors to the main contractor’s DLP obligations.
  5. Oblige contractor to leave O&M manuals and an as-built BIM model to simplify later defect tracing.
  6. Link final payment release to: (a) cleared punch list, (b) submission of all test reports, (c) Building Official’s occupancy clearance, and (d) a “No Pending Defect” certification signed by owner’s consultant.

7. Enforcement & Remedies

  • CIAC Arbitration – primary forum for construction disputes; awards often order release or forfeiture of retention and direct specific performance to remedy defects.
  • Regular Civil Courts – for tort-based or Article 1723 claims, especially when collapse causes injury.
  • Administrative sanctions – PCAB suspension, DPWH blacklisting for public projects.
  • Insurance recovery – Owner may claim under CAR policy and subrogate vs. contractor.

8. Key Take-aways for Stakeholders

  • Owners – negotiate an extended DLP (18-24 months) for high-risk seismic retrofits; keep meticulous defect logs.
  • Contractors – budget contingencies for rectification; maintain insurance covering the full DLP.
  • Design professionals – document code compliance; supervise works to dilute Article 1723 exposure.
  • Building Officials – may condition occupancy on posting of the warranty security.