1. Constitutional & Policy Foundations
| Provision | Key Guarantees for Occupants |
|---|---|
| Art. III, §1 | No person may be deprived of life, liberty, or property without due process of law. |
| Art. III, §9 | Private property shall not be taken for public use without just compensation. |
| Art. XII, §2 (Regalian Doctrine) | All lands of the public domain belong to the State; only agricultural, alienable & disposable (A & D) lands may be conveyed. |
| Art. XIII, §9–10 | Mandate for urban land-reform, social housing, relocation, and compensation for under-privileged and homeless citizens. |
| Art. II, §22 / IPRA (R.A. 8371) | Recognition of ancestral domains & requirement of free, prior & informed consent (FPIC) plus compensation where State action affects IP lands. (Judiciary eLibrary) |
2. Statutory Framework at a Glance
| Law | What It Covers | Core Due-Process / Compensation Rules |
|---|---|---|
| Public Land Act (C.A. 141) & R.A. 10023 | Titling A & D land via homestead, free patent, or judicial confirmation | Applicant must prove occupation & cultivation; long-term occupancy never ripens into title if land is still inalienable. |
| Urban Dev. & Housing Act (UDHA, R.A. 7279, 1992) | Eviction/demolition of under-privileged & homeless | §28 lists the famous “Ten UDHA Safeguards” (notice, consultation, court order, humane hours, presence of LGU/PCUP, relocation, etc.). (Refworld) |
| R.A. 10752 (2016) Right-of-Way Act | Acquisition of land/structures for national infrastructure | Prefers negotiated sale; if expropriation ensues, just compensation = current market value + replacement cost of improvements, incl. those built by informal settlers. (Department of Public Works and Highways) |
| Comprehensive Agrarian Reform Law (R.A. 6657) & CARPER (R.A. 9700) | Compulsory acquisition of private & gov’t agricultural land | Land Bank valuation formula; owners & farmer-beneficiaries both enjoy notice & hearing before DARAB. (Wikipedia) |
| Indigenous Peoples’ Rights Act (R.A. 8371) | Ancestral domains | No project may proceed without FPIC; the Ancestral Domains Fund (₱130 M start-up) finances compensation where domains are impaired. (FAOLEX Database) |
3. Due-Process Triggers for Long-Term Occupants
Reversion & Recovery of Public Land
- The Solicitor General or DENR may sue for reversion; occupants are entitled to notice, answer, and full trial.
- Republic v. CA & Naguit clarified that an occupant can only perfect title if land was already declared A & D before the filing of an application. (Lawphil)
Eviction/Demolition under UDHA
- City of Manila v. Banayad (G.R. 247009, 6 Feb 2024) annulled a demolition because LGU skipped the §28 consultation & relocation steps. (RESPICIO & CO.)
Right-of-Way for Infrastructure
- Under R.A. 10752, informal settlers can neither veto projects nor claim land ownership, yet are owed replacement cost + relocation; DPWH must craft a Land Acquisition, Resettlement & Rehabilitation Plan (LARRP) with public consultations. (Department of Public Works and Highways)
Ancestral Domains
- The NCIP issues a Certification Pre-condition only after FPIC assemblies; absence of FPIC voids any State grant or project permit. (WIPO)
4. Elements of Procedural Due Process (UDHA §28)
“Eviction or demolition shall be discouraged. It may occur only when…”
| Element | Practical Translation |
|---|---|
| (a) Danger areas or gov’t projects | Must be specifically certified by LGU/agency. |
| (b) 30-day written notice | Personal service + barangay posting. |
| (c) Consultation with affected families | Minutes signed by reps, PCUP, & NGOs. |
| (d) Court order (general rule) | Exception: on-going illegal construction, danger zones. |
| (e) Presence of uniformed police & LGU medics | To prevent violence, provide first aid. |
| (f) Humane hours & weather | 8 AM-5 PM; not on weekends/holidays/rainy days. |
| (g) Relocation or financial assistance | Adequate services, possession certificates, transport. (hudcc.gov.ph) |
Failure of any element renders the demolition void and officials may face civil & criminal liability (Anti-Graft Act; Art. 32, Civil Code).
5. Substantive Due Process & Just Compensation
| Taking Context | How Compensation Is Valued |
|---|---|
| Expropriation (Rule 67, RoC) | Judicially fixed FMV as of filing date + interests (6% p.a.). |
| R.A. 10752 ROW | Negotiated FMV (zonal or assessor’s value, whichever higher) + replacement cost of structures/crops, paid within 7 days of deed signing; if parties refuse, agency deposits 100% FMV + replacement cost in court. (Department of Public Works and Highways) |
| UDHA Relocation | Disturbance compensation (often ₱18k–₱60k/household per DHSUD circulars) + onsite/offsite housing; funds chargeable to project proponent. (DILG) |
| Ancestral Domains | Monetary or land-for-land compensation drawn from the Ancestral Domains Fund; loss of cultural sites may be compensated in kind (e.g., ceremonial areas). (Digest PH) |
| Agrarian Reform | Land Bank’s basic formula (MV = (Capitalized Net Income) + 10% of MV improvements) confirmed by SC in Land Bank v. Heirs of Montalvan (2023). (Lawphil) |
6. Can Long-Term Possession Create Ownership?
- Against the State: Prescription does not run (Art. 1113 Civil Code; §47 C.A. 141).
- Exception—Residential Free Patent (R.A. 10023): Ten-year tax declaration + 30-year actual, open, continuous occupation of A & D land allows titling up to 200 sq m (city) / 750 sq m (rural).
- Equitable Considerations: Courts occasionally award reimbursement or builders-in-good-faith value for improvements when government later classifies land for public use (see Republic v. CA, G.R. 170375, 2010). (Lawphil)
7. Recent Jurisprudence & Trends (2024-2025)
| Decision | Take-Away |
|---|---|
| City of Manila v. Banayad (2024) | Struck down summary demolition absent UDHA §28 compliance even in “danger zones.” (RESPICIO & CO.) |
| Heirs of Malabanan 2024 Re-examination | Re-affirmed doctrine that Declaration of A & D status — not mere occupation time-span — is sine qua non for prescription vs. State. (Lawphil) |
| Senate Bill 1874 (pending) | Seeks to double relocation assistance and criminalize non-issuance of 30-day notice. (legacy.senate.gov.ph) |
8. Administrative Mechanisms
| Body | Mandate Relevant to Occupants |
|---|---|
| DHSUD / NHA | Socialized housing, relocation site development. |
| Presidential Commission for the Urban Poor (PCUP) | Pre-demolition conferences; monitors UDHA compliance; may recommend halting illegal demolitions. (Judiciary eLibrary) |
| DPWH ROW Task Force | Implements LARRP & compensation under R.A. 10752. |
| NCIP | FPIC facilitation; ancestral-domain compensation. |
| DAR / DENR / OSG | Reversion suits; CARP coverage; land classification. |
9. Practical Checklist for Lawyers & Communities
Verify Land Status
- Check DENR land-classification maps; obtain Lot Data/CLAS.
Demand Documentary Compliance (for eviction/demolition)
- Written notice, consultation minutes, court order, approved relocation plan.
Compute Entitlements Early
- Gather tax declarations, assessor’s FMV, photos of improvements, receipts.
Invoke Administrative Remedies First
- File protest with PCUP/DHSUD; request DPWH mediation under §4 R.A. 10752 IRR.
Judicial Relief
- Rule 65 certiorari for grave abuse; Rule 67 counter-claims in expropriation; Acción Reivindicatoria if State title is questionable.
10. Key Take-Home Rules
- No title ≠ no rights. Even squatters on government land are constitutionally protected against arbitrary dispossession and entitled to humane relocation or compensation where the law so provides.
- Due process is two-tiered: procedural (proper notice/hearing) and substantive (fair reason + fair price).
- Compensation is context-specific: ROW Act, UDHA, CARP, and IPRA each supply distinct formulas; always identify the applicable statute first.
- Long-term occupancy alone rarely defeats the Regalian Doctrine—but it can ripen into statutory or equitable reliefs (free patent, builders-in-good-faith, disturbance pay).
- Recent Supreme Court cases (2024-2025) have tightened enforcement of UDHA safeguards and clarified land-classification prerequisites—making procedural vigilance more critical than ever.
Prepared: 1 June 2025 (GMT+8).