Force Majeure vs Fortuitous Event Under Philippine Law: Key Differences and Contract Effects

In the realm of Philippine civil law, the terms "force majeure" and "fortuitous event" are often used interchangeably. However, while they share a common legal effect—the preservation of a debtor from liability for non-performance—they possess distinct conceptual roots. For legal practitioners, business owners, and contractors in the Philippines, understanding these nuances is critical for risk management and contract enforcement.


1. Conceptual Definitions

Under Article 1174 of the Civil Code of the Philippines, the general rule is established:

"Except in cases expressly specified by the law, or when it is otherwise declared by stipulation, or when the nature of the obligation requires the assumption of risk, no person shall be responsible for those events which could not be foreseen, or which, though foreseen, were inevitable."

Fortuitous Event (Caso Fortuito)

Strictly speaking, these are Acts of God. These are events that happen totally independent of human intervention.

  • Examples: Earthquakes, typhoons, volcanic eruptions, lightning strikes, and floods.

Force Majeure (Fuerza Mayor)

These are Acts of Man. These refer to events that arise from human agency but are of such a nature that the debtor cannot resist or prevent them.

  • Examples: War, riots, insurrections, robberies involving violence or intimidation, and government-mandated lockdowns (as seen during the COVID-19 pandemic).

2. The Four Requisites for Exemption

To successfully invoke a fortuitous event as a defense to escape liability for breach of contract, the Philippine Supreme Court (e.g., in Metro Concast Steel Corp. v. Allied Bank) consistently requires the concurrence of four elements:

  1. Independent Will: The cause of the breach must be independent of the will of the debtor.
  2. Unforeseeability or Inevitability: The event must be either impossible to foresee, or if it can be foreseen, it must be impossible to avoid.
  3. Impossibility of Performance: The event must be of such a character as to render it impossible for the debtor to fulfill his obligation in a normal manner.
  4. Freedom from Negligence: The debtor must be free from any participation in, or aggravation of, the injury to the creditor.

3. Key Differences: Origin and Application

While the legal effect is usually the same, the distinction matters when interpreting specific contractual clauses.

Feature Fortuitous Event (Caso Fortuito) Force Majeure (Fuerza Mayor)
Source Nature / Natural occurrences. Human intervention / Third-party acts.
Foreseeability Often predictable to an extent (e.g., typhoon seasons) but unavoidable. Often sudden and political or social in nature.
Core Element "Act of God." "Act of Man."

4. Effects on Contracts

When a valid fortuitous event occurs, it generally results in the extinguishment of the obligation or the suspension of performance without penalty.

A. General Rule: Extinguishment

If the thing to be delivered is determinate (specific) and it is lost due to a fortuitous event, the obligation is extinguished. The debtor is not liable for damages.

B. Exceptions (When Liability Remains)

Even if an event is truly "fortuitous," a party may still be held liable in the following scenarios:

  1. Express Provision of Law: For example, when the debtor is already in mora (legal delay) before the event occurred.
  2. Contractual Stipulation: If the parties explicitly agreed that the debtor would be liable even in cases of caso fortuito.
  3. Assumption of Risk: When the nature of the obligation requires the assumption of risk (e.g., insurance contracts).
  4. Generic Obligations: Under the principle "genus nunquam perit" (genus never perishes), if the obligation is to deliver a generic thing (like money or a specific amount of rice), a fortuitous event does not excuse the debtor.

5. The "Doctrine of Supervening Event"

In some cases, the event doesn't make performance impossible, but rather manifestly difficult beyond the contemplation of the parties. This is covered under Article 1267 (The Doctrine of Unforeseen Events):

"When the service has become so difficult as to be manifestly beyond the contemplation of the parties, the obligor may also be released therefrom, in whole or in part."

This is the Philippine equivalent of the "Rebus Sic Stantibus" principle, allowing courts to grant equitable relief when the contractual equilibrium is totally destroyed.


6. Practical Considerations for Drafting

To protect against the ambiguity of Philippine law, contracts should include a well-defined Force Majeure Clause.

  • Specify the list: Explicitly include "epidemics/pandemics," "government regulations," or "labor strikes" to avoid litigation over whether an act of man counts as force majeure.
  • Notice Requirements: Require the affected party to notify the other within a specific timeframe (e.g., 72 hours) to validly invoke the clause.
  • Mitigation: State that the party invoking the clause must show they took reasonable steps to minimize the impact.