Process to Remove Building Permit from Property in the Philippines

Process to Remove a Building Permit from Property in the Philippines

Introduction

In the Philippines, a building permit is a crucial regulatory document issued by local government units (LGUs) to authorize the construction, alteration, repair, or demolition of structures on a property. Governed primarily by Presidential Decree No. 1096 (PD 1096), also known as the National Building Code of the Philippines, and its Implementing Rules and Regulations (IRR), building permits ensure compliance with safety, zoning, and environmental standards. However, circumstances may arise where a property owner seeks to remove or revoke such a permit from the property's records. This could stem from erroneous issuance, abandonment of the project, violations of code provisions, or the need to clear encumbrances for property transactions.

Removing a building permit is not a routine administrative task but a formal legal process that involves demonstrating valid grounds and adhering to procedural requirements. It is distinct from permit expiration, which occurs automatically under certain conditions, and focuses on actively nullifying or expunging the permit's effects on the property. This article provides a comprehensive overview of the process within the Philippine legal context, including grounds, procedures, requirements, and potential implications.

Legal Framework Governing Building Permits and Their Removal

The primary law regulating building permits is PD 1096, enacted in 1977 and amended over time to incorporate modern standards. Key provisions relevant to removal include:

  • Section 301: Mandates that no person, firm, or corporation shall construct, alter, repair, convert, use, occupy, move, demolish, or add to a building/structure without first obtaining a building permit from the Building Official.

  • Section 306: Empowers the Building Official to suspend or revoke a building permit for violations of the Code, falsification of documents, or non-compliance with terms and conditions. This section forms the core basis for permit removal.

  • Section 307: Addresses permit expiration, stating that a permit becomes null and void if work does not commence within one year from issuance or if work is suspended or abandoned for 120 days.

Supporting legislation includes:

  • Republic Act No. 7160 (Local Government Code of 1991): Devolves authority to LGUs, allowing cities and municipalities to enforce building regulations through their Office of the Building Official (OBO). Local ordinances may supplement national laws, providing specific procedures for permit revocation.

  • Department of Public Works and Highways (DPWH) Guidelines: The DPWH, through its Bureau of Design and other units, issues clarifications and uniform interpretations of the Building Code.

  • Civil Code Provisions: Articles 428 and 477 of the Civil Code pertain to property ownership and the right to seek removal of encumbrances, which may indirectly apply if a permit creates a lien or restriction on the title.

  • Environmental and Zoning Laws: Laws such as Republic Act No. 9275 (Clean Water Act), Republic Act No. 8749 (Clean Air Act), and Presidential Decree No. 1586 (Environmental Impact Statement System) may intersect if permit removal involves environmental non-compliance.

Jurisprudence from the Supreme Court and lower courts emphasizes due process in permit revocation. For instance, cases like City of Manila v. Chinese Community of Manila (G.R. No. L-14355, 1919) and more recent rulings underscore that administrative actions must afford notice and hearing to affected parties.

Grounds for Removing a Building Permit

Permit removal is not granted arbitrarily; it requires justifiable grounds. Common bases include:

  1. Erroneous Issuance: If the permit was granted based on false information, incomplete documents, or misinterpretation of zoning laws (e.g., the property is in a flood-prone area prohibited for construction).

  2. Non-Commencement or Abandonment: As per Section 307 of PD 1096, automatic nullification occurs, but formal removal may be sought to update records, especially if the permit is annotated on the property title.

  3. Violations of Building Code: Non-compliance with safety standards, such as substandard materials, unauthorized changes to plans, or failure to secure ancillary permits (e.g., electrical, mechanical).

  4. Public Safety or Nuisance Concerns: If the proposed structure poses risks to health, safety, or the environment, as determined by inspections or complaints.

  5. Change in Property Ownership or Use: New owners may petition for removal if they abandon the original plans, or if the property is repurposed (e.g., from residential to agricultural).

  6. Court Orders or Administrative Decisions: Revocation may follow judicial rulings, such as in expropriation cases or disputes over land titles under Torrens system (Republic Act No. 26).

  7. Expiration by Law: While automatic, owners may request official declaration of nullity to clear encumbrances.

Note that removal does not retroactively validate illegal constructions; any unauthorized work may still require demolition or penalties under Section 213 of PD 1096.

Step-by-Step Process for Removing a Building Permit

The process typically involves the OBO of the concerned LGU, with potential appeals to higher authorities. While procedures may vary slightly by locality (e.g., Manila vs. rural municipalities), the general steps are as follows:

  1. Preliminary Assessment: The property owner or authorized representative assesses the grounds for removal. Consult with a licensed architect, engineer, or lawyer familiar with local building regulations to evaluate viability.

  2. Filing a Petition or Application: Submit a formal written petition to the OBO. This should include:

    • A detailed explanation of the grounds for removal.
    • Reference to specific provisions of PD 1096 or local ordinances.
    • Sworn affidavit attesting to facts.

    In some LGUs, a specific form (e.g., Application for Permit Cancellation) is available.

  3. Submission of Required Documents: Attach supporting evidence (detailed in the next section). Pay any applicable filing fees, which vary by LGU but typically range from PHP 500 to PHP 5,000, depending on property value.

  4. Review and Inspection: The OBO reviews the petition and may conduct a site inspection to verify claims (e.g., no construction has started). This step ensures compliance with due process.

  5. Notice and Hearing: If the permit involves third-party interests (e.g., contractors or neighbors), the OBO issues notices for a hearing. Parties can present evidence, akin to administrative proceedings under the Administrative Code of 1987.

  6. Decision by the Building Official: The OBO issues a written order granting or denying the removal. If granted, the permit is revoked, and records are updated. Annotations on the property title (if any) are canceled through coordination with the Register of Deeds.

  7. Annotation and Recording: For properties under the Torrens system, file the revocation order with the Register of Deeds to remove any notations from the certificate of title.

  8. Appeals if Denied: If the petition is denied, appeal to the LGU's Sangguniang Panlungsod/Bayan within 15 days, then to the DPWH Secretary, and ultimately to the courts via certiorari under Rule 65 of the Rules of Court.

The entire process may take 30 to 90 days, depending on LGU efficiency and case complexity. Delays can occur due to hearings or oppositions.

Required Documents and Fees

To initiate removal, prepare the following:

  • Original building permit and approved plans.
  • Proof of ownership (e.g., Transfer Certificate of Title, Tax Declaration).
  • Affidavit of non-commencement or abandonment.
  • Inspection reports or certifications from relevant agencies (e.g., DENR for environmental clearance).
  • Payment receipts for any outstanding fees or penalties.
  • Notarized petition letter.
  • Identification documents of the applicant.

Fees include administrative charges, inspection fees, and possible penalties for violations. LGUs set these via ordinances; for example, Quezon City charges based on floor area, while smaller municipalities have flat rates.

Involved Authorities and Stakeholders

  • Office of the Building Official (OBO): Primary agency for processing.
  • Local Government Unit (LGU): Oversees through the city/municipal engineer.
  • Department of Public Works and Highways (DPWH): For appeals or national-level interpretations.
  • Register of Deeds: For title annotations under the Land Registration Authority (LRA).
  • Other Agencies: Depending on context, involvement from the Housing and Land Use Regulatory Board (HLURB) for subdivisions, or the Department of Environment and Natural Resources (DENR) for ecological issues.
  • Stakeholders: Property owners, architects/engineers, contractors, and potentially affected neighbors or complainants.

Potential Challenges and Remedies

Challenges include bureaucratic delays, opposition from interested parties, or insufficient evidence. Remedies involve:

  • Seeking mandamus if the OBO unreasonably delays action.
  • Filing complaints with the Ombudsman for graft or inefficiency.
  • Engaging in alternative dispute resolution for private conflicts.

Non-compliance with removal orders can lead to fines (up to PHP 20,000 per violation under PD 1096) or imprisonment.

Implications of Permit Removal

Successful removal clears the property for new permits or uses, potentially increasing market value by removing restrictions. However, it does not absolve past liabilities, such as unpaid fees. Owners should ensure all related permits (e.g., occupancy) are also addressed.

In summary, removing a building permit in the Philippines is a structured process rooted in administrative law, emphasizing due process and compliance. Property owners are advised to engage professionals to navigate complexities, ensuring alignment with national and local regulations for a smooth outcome.