Proper Procedure for Terminating a Residential Construction Contract with a Contractor

Terminating a construction contract is a high-stakes legal maneuver. In the Philippine jurisdiction, residential projects are primarily governed by the Civil Code of the Philippines, supplemented by the Construction Industry Authority of the Philippines (CIAP) Document 102, which serves as the standard for conditions of contract in the local industry.

To terminate a contract without falling into a "breach of contract" trap yourself, you must strictly adhere to procedural and substantive requirements.


1. Establishing Legal Grounds for Termination

One cannot simply terminate a contract because of a change of heart. Termination must be rooted in specific grounds defined by law or the contract itself.

Grounds for the Owner (Principal)

  • Substantial Breach: Persistent failure by the contractor to provide enough skilled workers or proper materials.
  • Failure to Progress: Undue delays that make it impossible to complete the project within the stipulated timeframe.
  • Violation of Laws: Disregard of local building codes, safety ordinances, or labor laws.
  • Insolvency: The contractor enters bankruptcy or makes an assignment for the benefit of creditors.

Grounds for the Contractor

  • Non-payment: Failure of the owner to pay certified progress billings within the agreed period.
  • Work Suspension: If the owner orders a stoppage of work for an unreasonable period (usually 30+ days) through no fault of the contractor.

2. The Procedural Roadmap

The "How" is as important as the "Why." Deviating from the agreed-upon notice procedure can make an otherwise valid termination illegal.

Step 1: The Notice of Default (The "Cure Period")

Before terminating, the aggrieved party must usually issue a Notice of Default. This formal letter must:

  • Identify the specific provision of the contract being violated.
  • Demand that the violation be corrected.
  • Provide a "cure period" (typically 5 to 15 days depending on the contract or CIAP 102) for the contractor to rectify the issue.

Step 2: The Notice of Termination

If the contractor fails to "cure" the breach within the window provided, a formal Notice of Termination is issued. This notice should state that the contract is officially dissolved and specify the date when the contractor must vacate the premises.

Step 3: Joint Inventory and Site Handover

Upon termination, both parties should ideally conduct a joint inventory of:

  • Materials already paid for by the owner that remain on-site.
  • The actual percentage of completion (to determine final payables or overpayments).
  • The condition of the equipment being removed.

3. Financial Implications and "Take-Over"

Termination does not end the financial relationship; it shifts it into an accounting of damages.

  • The 10% Retention Money: The owner typically withholds this until the project is finished by a new contractor to cover any latent defects found later.
  • The Performance Bond: The owner may call upon the contractor’s surety bond to cover the additional costs of hiring a new contractor to finish the work.
  • Cost of Completion: Under Philippine law, if the cost to finish the house exceeds the original contract price, the original contractor may be held liable for the price difference as liquidated damages.

4. Dispute Resolution: CIAC Jurisdiction

Most Philippine construction contracts include an arbitration clause. Under Executive Order No. 1008, the Construction Industry Arbitration Commission (CIAC) has original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines.

Even if the contract does not explicitly mention the CIAC, if it is a construction dispute, the courts will often refer the parties to arbitration first.


5. Critical Best Practices

Document Everything: Keep a logbook of delays, take photos of substandard work, and ensure all communication regarding "warnings" is sent via registered mail or courier with a return receipt. Avoid "Self-Help": Do not forcibly remove a contractor or seize their tools without a written notice of termination, as this could lead to criminal charges (e.g., Grave Coercion) or civil liability.

Summary Table: Termination Checklist

Phase Action Required Legal Basis
Warning Notice of Default (with Cure Period) Contractual Compliance
Execution Notice of Termination Civil Code / CIAP 102
Valuation Joint Inventory & Progress Audit Accounting of Damages
Resolution Demand for Bond/Arbitration CIAC / RTC