1. Concept and Sources of Law

Layer Primary Authorities
Constitutional 1987 Constitution, Art. III §9 (private property shall not be taken for public use without just compensation); Art. XII §3 (expropriation of lands of public domain)
Civil Code Arts. 649-657 (legal easement of right-of-way between private estates); Arts. 613-637 (general rules on easements); Arts. 428-435 (attributes of ownership); Art. 435(3) (expropriation)
Special Statutes 1. Republic Act (RA) 10752, “Right-of-Way Act” (2016) – governing national government infrastructure projects, superseding portions of RA 8974 (2000)
  1. RA 11203 (2019) in respect of NFA lands and easements for grains corridors
  2. Power industry laws (e.g., RA 9136, RA 9513) for transmission-line easements | | Administrative | DPWH Implementing Rules and Regulations (IRR) of RA 10752 (DO 65-2018, DO 11-2020); National Transmission Corporation (TRANSCO) ROW Manual; DENR DAO 2007-29 (land valuation) | | Procedural | Rule 67, Rules of Court (expropriation); Rule 141 §7 (filing fees) |

2. Distinction: Easement vs Expropriation

Item Easement of Right-of-Way Full Taking (Expropriation)
Ownership Title stays with servient estate; only a limited real burden is imposed Title transferred to the State/party
Basis Arts. 649-657 Civil Code (private-to-private) or special law (utilities) Constitution + Rule 67 + RA 10752
Compensation “Proper indemnity” – typically (a) value of area actually occupied, (b) consequential damages, minus consequential benefits “Just compensation” = fair market value of the property taken + damages to remainder
Who may invoke Dominant owner (neighboring landlocked parcel); public utilities with statutory power (e.g., NGCP) Any expropriating authority (Government, GOCC, LGU, utility with delegated power)
Formula trigger Must prove (a) claimant’s property is surrounded, (b) no adequate outlet, (c) payment of indemnity Necessity or public purpose; filing of complaint in court if negotiation fails

In practice, courts often award just compensation even in easement cases where the burden is so extensive that it is equivalent to a taking (see NPC v. Heirs of Macabangkit Sangkay, G.R. 165828, August 24 , 2011).


3. Private-to-Private Easements (Civil Code)

3.1 Requisites under Article 649

  1. Immovable is surrounded by other estates with no adequate outlet.
  2. Right-of-way must be indispensable for proper use.
  3. Way chosen shall be the shortest and least prejudicial to servient estate.
  4. Dominant owner indemnifies servient owner:

“He who establishes an easement of right-of-way is bound to indemnify the owner of the servient estate for the value of the land occupied, and for any damage caused to the servient estate.” – Art. 649 ¶2

3.2 Amount of Indemnity

The Code is silent on a formula; courts have developed standards:

Component Usual judicial measure
Land value Market value of strip actually used, multiplied by area burdened; often discounted (50 % rule) if passage is non-exclusive
Consequential damages Diminution in value of remainder, crop loss, disruption
Consequential benefits Increase in value of servient land (offset)
Construction costs If servient owner must build fences or drainage because of the easement, costs are chargeable to dominant owner

Because procedure is ordinary civil action, parties sometimes request Commissioners (Rule 67 analogy) to compute damages.


4. Government Acquisition for Infrastructure (RA 10752)

4.1 Policy Shift

RA 10752 adopted the “negotiated purchase first” model:

  1. Offer: Implementing Agency (IA) offers the owner the amount calculated per §6.
  2. Acceptance and payment within 30 days → conveyance deed + transfer of title.
  3. Failure to agree → expropriation suit under Rule 67.

4.2 Components of Compensation (Sec. 5)

Item
Land Current market value from BIR zonal valuation or Appraisal Committee if outdated
Structures Replacement cost new, using BCDA guidelines, no depreciation
Crops/Trees Current market price at time of taking, based on PSA data
Disturbance/Relocation (i) ₱15,000–₱100,000 disturbance compensation for lawful occupants; (ii) livelihood assistance (DO 13-2019)
Professional/Transfer Taxes Capital gains, DST, registration, and documentary stamps shouldered by IA

Advance entry: Upon filing, IA deposits: 100 % of BIR zonal value + 1 yr taxes + replacement cost of improvements. Court then issues writ of possession (Sec. 9).

4.3 Special exemptions

  • Ancestral domains: Must comply with IPRA (RA 8371) and obtain FPIC.
  • Agrarian lands: Prior DAR conversion or retention approval.
  • Heritage sites: NHCP clearance.

4.4 Tax treatment

  • Proceeds are capital gains subject to 6 % CGT (unless familial or juridical exemptions apply).
  • If owner is a corporation, compensation is ordinary income (corporate income tax).
  • IA shoulders withholding taxes per §6(e).

5. Valuation Principles Used by Courts

Principle Explanation
Time-of-taking rule Value is fixed when the title is transferred or possession is disturbed, whichever is earlier (Republic v. Castillo, G.R. 189109, Jan 18 , 2022).
Comparable sales Court prefers actual sales within vicinity over zonal values if evidence is credible.
Unit rule vs before-and-after rule Land taken valued separately (unit) or remainder depreciation measured (before-and-after).
Consequential damages/benefits Article 652 (as applied to ROW) – benefits offset damages, but not land value.
Interest 12 % p.a. (until July 1 , 2013) then 6 % p.a. (Bangko Sentral circulars) on any deficiency from time of taking until full payment.

6. Illustrative Jurisprudence

Case G.R. No. Ratio
Reiterina v. Republic (2021) 253497 The 2021 DPWH offer letter is evidence but not conclusive; court must still receive expert appraisal.
NPC v. Sangkay (2011) 165828 69-kV transmission-line easement deemed constructive taking; owner entitled to FMV of entire burdened strip.
Republic v. Lubrica (2010) 207825 Land zoned agricultural but used for resort; resort’s income stream considered in valuation.
Spouses Abalos v. Philex (1994) 94695 Intra-private right-of-way must pick route least prejudicial even if slightly longer.
Reyes v. Lim (2001) 180986 Indemnity covers rental value for temporary construction easement.

7. ROW Compensation for Electric, Water, and Telecom Utilities

Sector Governing Issuances Typical ROW Width Compensation Peculiarities
Transmission (NGCP) Energy Reg. Comm. Res. 4-2015; NGCP ROW Manual 15–20 m for 69 kV; 35 m for 230 kV Annual rental (10 % of zonal value) if only aerial clearance; full FMV if tower footing occupies land
Distribution (MERALCO et al.) DSO franchise + ERC ROW Rules 6 m for 13.8 kV lines Mostly negotiated easements; minimal disturbance indemnity
Water districts PD 198; LWUA Model ROW Manual Pipe diameter + 2 m both sides Reinstatement of pavement costs charged to utility
Telcos RA 7925; DICT ROW Guidelines 2019 Micro-cells on poles/rooftops Vendors often accept lease rental instead of sale

8. Procedural Roadmap for Practitioners

  1. Due diligence: Verify title (clean OCT/TCT), occupants, liens, CARP status.
  2. Appraisal: Commission accredited RE appraiser; use at least three comparable sales; adjust for time, location, physical characteristics.
  3. Negotiation: Serve written offer with appraisal report, plan-profile-cross-section.
  4. Payment/Deed execution: Notarize Deed of Sale, Deed of Donation, or Easement Agreement; annotate on TCT.
  5. If negotiation fails: Prepare verified Complaint for Expropriation with (a) authority to take, (b) urgency certification, (c) deposit computation.
  6. Court intervention: Secure immediate possession via issuance of writ; commissioners’ hearings for valuation.
  7. Finality: Pay difference within 30 days from judgment; secure Final Deed of Transfer; register.
  8. Post-acquisition audit: COA requires validation of supporting docs (COA Circular 2020-009).

9. Common Pitfalls & Practical Tips

For Implementing Agencies

  • Lapses in authority: Always attach authenticated Sangguniang Resolution (LGU) or Office Order (line agency).
  • Untimely deposits: Delay in opening escrow subjects officers to audit disallowance.
  • Ignoring usufructuaries/lessees: They are indispensable parties under Art. 597; secure waivers or pay disturbance.

For Landowners

  • Undocumented improvements: Document with building permit, photos, receipts; otherwise DPWH will treat them as salvage value only.
  • Estate settlement issues: If owner deceased, secure extra-judicial settlement and EJS-CAR before negotiating.
  • Tax compliance: Secure updated RPT clearance; unpaid taxes are deductible from proceeds.

10. Future Developments

  1. Valuation Reform Bill (House Bill 6558, Senate Bill 364): proposes using “updated schedule of market values” by LGUs every three years; may harmonize zonal and SMV systems.
  2. Digital ROW Platforms: DPWH Piloting e-ROW system to integrate LAMS, e-Title, and PSA price indices for faster appraisal (target nationwide rollout 2026).
  3. Green Infrastructure: Proposed “Blue-Green Easements Act” will expand compensable items to include ecosystem services lost (mangrove belts, riparian buffers).

11. Conclusion

Compensation for right-of-way in the Philippines operates on two parallel tracks:

  • Civil Code easements balance neighborly necessity with the owner’s right to be made whole, using indemnity grounded in fair market value and consequential damages.*
  • Government and utility acquisitions apply the constitutional standard of just compensation, now codified in RA 10752, coupling transparent appraisal methods with streamlined possession.*

While formulas differ, the unifying principle is restorative – owners should emerge financially in the same position as if their property had not been burdened, and the public (or dominant estate) should secure access critical to national development or land utility. Mastery of the statutes, jurisprudence, and valuation techniques outlined above equips practitioners to structure deals, prosecute or defend suits, and, ultimately, reconcile private rights with public necessity.


Prepared June 17 , 2025