Rights of Homebuyers for Delayed Turnover of Real Estate Properties

Investing in real estate is a significant milestone, but the excitement of acquiring a new home can quickly turn into frustration when developers fail to deliver the unit on time. In the Philippines, the law provides robust protections for homebuyers to ensure they are not left at a disadvantage due to project delays.

The primary governing law for these situations is Presidential Decree No. 957 (P.D. 957), also known as the Subdivision and Condominium Buyers' Protective Decree, as amended.


1. The Right to Stop Payment

Under Section 23 of P.D. 957, a buyer has the legal right to suspend installment payments if the developer fails to develop the subdivision or condominium project according to the approved plans and within the specified time limit.

  • Prior Notice: The buyer must notify the developer of the intention to stop payment due to the delay.
  • No Forfeiture: The developer cannot forfeit the payments already made or consider the buyer in default for exercising this right.
  • No Penalties: No installment payment shall be denied to the buyer, and no interest or penalty shall be imposed on the delayed payments during this period.

2. The Right to a Full Refund

If the buyer decides that they no longer wish to proceed with the purchase due to the delay, they are entitled to a refund of the total amount paid.

  • Total Amount: This includes the reservation fee, down payments, and all monthly installments.
  • Compounded Interest: The refund must include amortization interests but excluding delinquency interests, with interest at the legal rate (currently 6% per annum).
  • No Deductions: The developer is prohibited from deducting "administration fees" or "processing fees" from the refund amount if the cause of the cancellation is the developer's delay.

3. Application of the Maceda Law (R.A. 6552)

While P.D. 957 is the specific law for developer defaults, the Realty Installment Buyer Protection Act (Maceda Law) also applies to transactions involving installments.

However, there is a key distinction:

  • Under the Maceda Law, if a buyer defaults, they only get a 50% refund (after 2 years of payments).
  • Under P.D. 957, if the developer is at fault (delay), the buyer gets a 100% refund regardless of how many years of installments have been paid.

4. Remedies for Specific Performance

If the buyer still wants the unit despite the delay, they can demand Specific Performance. This is a legal action to compel the developer to:

  1. Finish the project.
  2. Turn over the unit immediately.
  3. Comply with the amenities and specifications promised in the marketing materials and the Contract to Sell.

5. Claims for Damages

Beyond a refund, a buyer may also sue for damages under the Civil Code of the Philippines. If the developer acted with fraud, negligence, or delay (mora), the buyer may be entitled to:

  • Actual/Compensatory Damages: To cover financial losses (e.g., rent paid elsewhere while waiting for the delayed turnover).
  • Moral Damages: If the delay caused physical suffering, mental anguish, or serious anxiety.
  • Exemplary Damages: Imposed by the court as a deterrent against public wrong.
  • Attorney’s Fees: Especially if the buyer was forced to litigate to enforce their rights.

Procedures for Recourse

Administrative Complaint (DHSUD)

The Department of Human Settlements and Urban Development (DHSUD), formerly the HLURB, has quasi-judicial jurisdiction over real estate disputes.

  1. Mediation: The DHSUD usually requires a mandatory mediation conference to see if the buyer and developer can reach an amicable settlement (e.g., a revised turnover date or a voluntary refund).
  2. Verified Complaint: If mediation fails, the buyer files a verified complaint. The DHSUD can issue orders for refunds, impose administrative fines on developers, and even revoke the developer’s License to Sell.

Judicial Action

While most cases are handled by the DHSUD, certain claims for damages or complex contractual disputes may be brought before the regular Regional Trial Courts.

Important Considerations

  • Grace Period: Check the "Contract to Sell." Most contracts include a "Grace Period" (usually 6 to 12 months) beyond the target date. The legal delay usually begins only after this period expires.
  • Force Majeure: Developers often cite "acts of God" or "unforeseen events" (like the pandemic or extreme weather) to justify delays. However, the DHSUD strictly scrutinizes these claims to ensure they are not used as an excuse for poor management.
  • Documentation: Always keep copies of the Contract to Sell, official receipts, and all written correspondence with the developer regarding the turnover date.