In the Philippines, the management and regulation of Road Right-of-Way (RROW) are critical for urban planning, public safety, and infrastructure development. Governed by a blend of presidential decrees, national laws, and administrative orders, the RROW defines the total width of land reserved for public passage, encompassing not just the pavement, but also shoulders, curbs, gutters, and sidewalks.
1. Legal Foundations of RROW
The standards for RROW in the Philippines are primarily derived from three major legal pillars:
- Presidential Decree No. 1096 (National Building Code of the Philippines): Establishes the relationship between building setbacks and road widths.
- Executive Order No. 113 (as amended): Classifies roads and sets the absolute minimum widths for national and local roads.
- Batas Pambansa Blg. 220 & PD 957: These govern socialized housing and open market subdivisions, respectively, dictating narrower RROW requirements for residential developments.
2. Classification-Based Width Standards
The Department of Public Works and Highways (DPWH) and the Department of the Interior and Local Government (DILG) enforce specific minimum widths based on the road's classification.
National Roads
National roads are the backbone of the Philippine transport network. Under DPWH standards:
- Minimum Width: Generally 20.00 meters.
- Expansion: For newly designated national roads or high-traffic corridors, the government often seeks a standard of 30.00 meters to accommodate future expansion, utility lines, and drainage.
Local Roads (Provincial, City, and Municipal)
Local government units (LGUs) manage these roads, but must adhere to minimums set by national law:
- Provincial Roads: Minimum of 15.00 meters.
- City/Municipal Roads: Minimum of 10.00 meters.
- Barangay Roads: Minimum of 6.00 meters.
3. RROW in Residential Subdivisions
For private developments and housing projects, the standards vary depending on the economic tier of the project.
| Development Type | Main Road (Min.) | Secondary Road (Min.) | Alley/Path (Min.) |
|---|---|---|---|
| PD 957 (Open Market) | 10.0 meters | 8.0 meters | 2.0 - 3.0 meters |
| BP 220 (Socialized) | 8.0 meters | 6.5 meters | 3.0 meters (Path) |
Note: These widths must include the carriage way (pavement), planting strips, and sidewalks.
4. Components of a Standard RROW
A Road Right-of-Way is not merely the "asphalt." Legally, it is composed of several zones that must fit within the mandated width:
- Carriageway: The portion intended for vehicular travel.
- Shoulders: The area adjacent to the carriageway for emergency stops and lateral support.
- Sidewalks: Minimum requirements often start at 1.20 meters for pedestrian safety.
- Drainage/Canals: Vital for flood control, usually situated at the edge of the RROW.
- Planting Strips: Buffer zones between the sidewalk and the curb.
5. Setbacks and The National Building Code
The National Building Code (NBC) dictates that the "Building Line" must be set back from the RROW boundary. The width of the RROW directly determines how far back a structure must be built:
- RROW of 10m to 19m: Requires a front setback of 5.00 meters (for commercial/industrial zones).
- RROW of 20m or more: Requires a front setback of 8.00 meters.
Failure to respect the RROW boundary is a common cause of "encroachment," which grants the government the right to summarily remove obstructions under the Public Assembly Act and various DPWH Department Orders (e.g., DO No. 73, series of 2014).
6. Acquisition and Just Compensation
Under Republic Act No. 10752 (The Right-of-Way Act), the government has the power of eminent domain to acquire private property for RROW. Key points include:
- Current Market Value: The government must offer the owner the current market value of the land.
- Replacement Cost: For structures and improvements affected by the RROW acquisition.
- Easements: In cases where the full title isn't taken, a legal easement may be imposed, limiting the owner's use of the land.
7. Penalties for Encroachment
Structures built within the RROW are considered "nuisances per se." The government reserves the right to:
- Issue notices of violation.
- Demolish structures at the owner's expense.
- Withhold building permits or certificates of occupancy.